| Rescheduled? | No |
| Outage Date: | Thursday, 11/12/09 |
| Outage Time: | 6:45 am - 9:00 am |
| Buildings Affected: | Poulton |
| Area of building: | rear of building |
| Outage Type: | Other |
| Description: | Preventive maintenance on the UPS. Before service takes place, Facilities must ensure that the fuel tanks on the generator are topped off and the generator can run 24 hours. |
| Reason: | Facilities must come over at 6:45 am on 11/12/09 and start up the generator. After it has run for 30 minutes, the UPS can be switched into bypass mode while the preventive maintenance takes place. When the PM is complete, Facilities must switch back to street power supported by the UPS. |
| Status: | Completed |
| Emergency? | No |
| Requestor Name: | Larry Bruce |
| Requestor Phone: | 202 687 3611 |
| RequestorEmail: | brucel@georgetown.edu |
| Other time(s) outage can be scheduled: | NO |